Introducing baselines for project management, available now!
Comments
-
Really happy to see this feature in Smartsheet and have been using it effectively. There is one item that doesn't quite seem to make sense with other smartsheet behavior for me.
The Variance shown is in absolute days between two dates - I understand a logic for that, however given the duration column is processed in working days rather than absolute this has been causing confusion in our teams.
Is this logic intentional - if so is there an option to change it?
-
My above comment is incorrect - I didn't test properly
-
@Morgan Kozol, I just wanted to follow up on your comments from May 25th of last year. Is it still the case that if we add rows/tasks to a sheet and the baseline has already been set, we need to reset it in order to update the sheet's baseline and populate the baseline fields for the new rows/tasks?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives