Partial Critical Path Display
Hello Support team,
I am having problem to display the full critical path. Basically, my project has 3 section and Critical path is highlighted only in the last section. The activities in section 1 and 2 can be complete in parallel. Could you help me on that?
Thanks
Answers
-
Is it possible the tasks in section 1 and 2 are not on the critical path? Depending on how the dates fall across the sections, they may not be.
Dale