%Complete

I am looking for a formula that will calculate % Complete based on two dates. I have been successful at getting this formula to work on projects that have already began but completed dates or not started dates are giving me a percentage that is negative or above 100. I would like projects that have not started to say "0" and projects completed to show "100". For example

Thank you for anyone who is able to support with this.

Best Answer

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer βœ“

    Try this...

    =IF((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row) > 1, 1, IF((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row) < 0, 0, (TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row))

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

Answers

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    Take your "original_formula" and drop it into a nested IF statement to say that if it is less than zero then output zero, if it is greater than 1, output 1, otherwise output the "original_formula".

    =IF(original_formula < 0, 0, IF(original_formula > 1, 1, original_formula))

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

  • Angela Campbell
    Angela Campbell ✭✭

    @Paul Newcome ,

    Thank you so much for the feedback. I keep getting an unparsable return. Am I using the () in the wrong spaces?

    =IF(((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)) < 1, ((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)) <0,0, IF(((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)) < 1, ((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row))>1,1,(((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)) < 1, ((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)))

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    What exactly is your original formula?

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

  • Angela Campbell
    Angela Campbell ✭✭

    @Paul Newcome

    =IF(((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)) < 1, ((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row)))

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer βœ“

    Try this...

    =IF((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row) > 1, 1, IF((TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row) < 0, 0, (TODAY() - [Screenshots for Job Aid Due Date]@row) / ([Go Live]@row - [Screenshots for Job Aid Due Date]@row))

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

  • Angela Campbell
    Angela Campbell ✭✭

    @Paul Newcome

    Thank you so very much!! I truly appreciate this!

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    Happy to help. πŸ‘οΈ

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

  • Morgan Stokes
    Morgan Stokes ✭✭

    Hello,


    I am using a similar formula to calculate % complete based on a start and end date. It works unless the start and end date are on the same day. In this case, it returns an error that it cannot divide by zero. Any suggestions?

    Formula: =IF((TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row) > 1, 1, IF((TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row) < 0, 0, (TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row)))


    Example error:


  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    @Morgan Stokes Try something like this...


    =IF(AND([Start Date]@row = [End Date]@row, TODAY() > [Start Date]@row), 1, IF((TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row) > 1, 1, IF((TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row) < 0, 0, (TODAY() - [Start Date]@row) / ([End Date]@row - [Start Date]@row))))

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!