Exceeding 100% Completion
How do I override the system to account for more than 100% Completion. For instance, the initial project accounted for 4 visits; and when the project was completed the client wanted an additional event. When I add that event the Completion still adds up to 100% and not to 125% to show that the project went over scope.
Answers
-
Hope you are fine, Please add a copy of your sheet or a screenshot (after removing or replacing any sensitive information). This will make it easier for me to provide the appropriate answer to your question.
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
I hope you're well and safe!
You'd have to add another column and a formula to calculate it manually or remove the dependency setting to have the current one set with a formula.
Make sense?
Would that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
Check out the Formula Handbook template!