Hey team - I have a STATUS drop down menu that I manually update, options are:
- Caution
- Complete
- Not Started
- Off Track
- On Track
- On Hold
- At Risk
- Canceled
However, I'm looking for a way for the STATUS to automatically change to Off Track if the TARGET COMPLETE DATE is in the past and the previous STATUS was anything other than Complete/Canceled/On Hold.
Is that possible?
Best Answer
-
Jmo,
Set the trigger to any value and add a condition below.
Select Where Target Complete Date and the drop down will give the in the past option.
Then you can set the cell value you want to change and to what.
I hope this helps.
Frank Smith, PMP
Assistant Director | IT Special Projects Mgr.
Oregon Parks & Recreation Department
If my response helps, please mark it as an accepted answer. 😎
Answers
-
Are you able to setup and Automation workflow that would Run when the Target complete date is reached. Where conditions that Status would not be set to those 3 statuses. To change the value in the Status cell to off target?
-
Jmo,
Have you tried using the new automated workflow, change a cell value?
I would create a workflow based upon the target date and then change the cell value (Status) based upon the criteria you want.
I would run the workflow daily or on a custom reoccurrence to make sure it was updated regularly.
I hope this helps.
Frank Smith, PMP
Assistant Director | IT Special Projects Mgr.
Oregon Parks & Recreation Department
If my response helps, please mark it as an accepted answer. 😎
-
@Joel Wells & @Frank.Smith - I took a look at the new Change Cell Value automation however, when I look for making the first condition of TARGET COMPLETE DATE "in the past" - it doesn't come up as an option (like when creating a filter in a sheet) but rather wants me to pick a date(s).
Not sure how to use that new automation feature to flip STATUS to Off Track once a date occurs in the past.
-
Jmo,
Set the trigger to any value and add a condition below.
Select Where Target Complete Date and the drop down will give the in the past option.
Then you can set the cell value you want to change and to what.
I hope this helps.
Frank Smith, PMP
Assistant Director | IT Special Projects Mgr.
Oregon Parks & Recreation Department
If my response helps, please mark it as an accepted answer. 😎
-
@Frank.Smith - I think you solved it!!!!
-
Glad I could help. The new change a cell functionality is a BIG improvement😉.
Frank Smith, PMP
Assistant Director | IT Special Projects Mgr.
Oregon Parks & Recreation Department
If my response helps, please mark it as an accepted answer. 😎
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65K Get Help
- 443 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 129 Brandfolder
- 150 Just for fun
- 70 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!