Incorrect Argument Set when using Networkdays
Hello, I try to calculate a working day date based on a given start date and adding 5 business days.
I am using this formula but keep getting an error.
Please advise.
=NETWORKDAYS([Campaign Start Date]@row + 5)
Answers
-
I hope you're well and safe!
You need to have two dates for it to work.
More info.
Did that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Thank You! Is there a way/workaround to do what I need:
Need: Add 15 business days to a given date (already in the sheet) and output a business day?
Thanks
-
Happy to help!
You'd use the WORKDAY function for that.
Did that work/help?
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Great that worked exactly how I wanted it - appreciate the help!
Follow up questions
- Does conditional formatting that counts days (highlight to red if more than 5 days out) count business days or calendar days?
- Does WORKDAY account for my sheets set holidays or do I manually have to exclude each holiday outside of weekends in the formula itself?
Thanks!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!