Chevron-based on Parent Task (level 1) dashboard graphic
I would like to add a visual to a Dashboard that is based on the top-level summary tasks of my project schedule. This would be a reader-friendly, consumable way to view a Gantt chart. I see that SmartSheets uses this visual for tracking internal training, and thus I have found it to be a helpful "quick glance" at progress. Can this be built for a dashboard?
Essentially the "Dominos pizza tracker" for my project schedule. Any advice?
Best Answer
-
Hello @E. Robert Shanfeld
I created a test with using the progress bar symbol & from there, I used that to be placed in a dashboard using a Metrics widget. See my sample setup below.
My Sample sheet with showing the progress bar for the task under the project & the overall progress bar. I used the formula below to calculate for the progress bar based on the % complete.
=IF(ISBLANK([% Complete]@row), "Empty", IF([% Complete]@row <= 0.24, "Quarter", IF([% Complete]@row <= 0.49, "Half", IF([% Complete]@row <= 0.99, "Three Quarter", IF([% Complete]@row = 1, "Full", "Empty")))))
I used the AVG function to calculate the overall % for the sub-tasks.
From there, in the dashboard - I had selected the first chunk which is for Project A.
Then I used a Metric Widget to have that progress bar reflect the overall status of Project A. Same goes for Project B & the following single Projects you have.
Let me know if this helps or if you have further questions & I misunderstood your question! Thank you~
Cheers,
Krissia
Answers
-
Hello @E. Robert Shanfeld
We currently do not have a programmed capability for that specific feature to replicate a tracker similar to the Domino's Pizza Tracker, but it is a really great idea! I recommend submitting an enhancement request to be considered for future development.
In the meantime, an alternate solution is to have the data be pulled into a Chart Widget & have this in a Dashboard. In the sample image below, I used the Stacked Bar type to showcase a progress for the projects. See sample image below for reference.
More information in the link below.
Let us know if you have further questions. Hope this helps!
Cheers,
Krissia
-
Hi Krissia--that is helpful for running a collection of projects (i.e. program or portfolio), however, I am looking to show progress within 1 project. I am looking to show which summary tasks are complete, and which are not. Could this be done based on a web widget of sorts?
-
Hello @E. Robert Shanfeld
I created a test with using the progress bar symbol & from there, I used that to be placed in a dashboard using a Metrics widget. See my sample setup below.
My Sample sheet with showing the progress bar for the task under the project & the overall progress bar. I used the formula below to calculate for the progress bar based on the % complete.
=IF(ISBLANK([% Complete]@row), "Empty", IF([% Complete]@row <= 0.24, "Quarter", IF([% Complete]@row <= 0.49, "Half", IF([% Complete]@row <= 0.99, "Three Quarter", IF([% Complete]@row = 1, "Full", "Empty")))))
I used the AVG function to calculate the overall % for the sub-tasks.
From there, in the dashboard - I had selected the first chunk which is for Project A.
Then I used a Metric Widget to have that progress bar reflect the overall status of Project A. Same goes for Project B & the following single Projects you have.
Let me know if this helps or if you have further questions & I misunderstood your question! Thank you~
Cheers,
Krissia
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives