On one of the columns, I can change the status to complete. When that cell is changed to complete,
Abbie G
✭✭
is there a way to record all the dates when the cells where changed to complete? Hopefully this makes sense.
Answers
-
Try inserting a date type column and then using a Record A Date automation triggered for when the status column changes to complete.
-
@Paul Newcome Thank you! Is it possible to get it for past cells that were changed to complete? I know I can get the data from cell history, but I'd like an entire column of it as well.
-
For cells that have already been changed, you will need to manually update those unfortunately.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives