On one of the columns, I can change the status to complete. When that cell is changed to complete,
is there a way to record all the dates when the cells where changed to complete? Hopefully this makes sense.
Answers
-
Try inserting a date type column and then using a Record A Date automation triggered for when the status column changes to complete.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
@Paul Newcome Thank you! Is it possible to get it for past cells that were changed to complete? I know I can get the data from cell history, but I'd like an entire column of it as well.
-
For cells that have already been changed, you will need to manually update those unfortunately.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.6K Get Help
- 371 Global Discussions
- 203 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives