formula for +40 days after Q
Trish Dillon
✭✭✭✭✭✭
hello,
thank you in advance
i am looking for a formula to auto calculate 40 calendar days after end of quarter.
which does not include holidays or weekends.
thoughts?
Thank u
Tags:
Answers
-
=WORKDAY(Lastdayofquarter@row, 40)