Workday Formula

Options

Hi,

I need help about WORKDAY formula. The start date for a task is 10/04/2021 and the duration of the task is 10 working days excluding weekend. I want a formula to calculate the due date which should be a work day only excluding weekend based on the start date and duration. Unfortunately, the WORKDAY formula is not taking into consideration the start date 10/04/2021 and it is giving me the due date of 10/18/2021 instead of 10/15/2021. I don't have dependencies enabled in my Project Settings and the formula I'm using is =WORKDAY([Start Date]@row, Duration@row). Please advise.

Thanks.

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!