Workday Formula
Hi,
I need help about WORKDAY formula. The start date for a task is 10/04/2021 and the duration of the task is 10 working days excluding weekend. I want a formula to calculate the due date which should be a work day only excluding weekend based on the start date and duration. Unfortunately, the WORKDAY formula is not taking into consideration the start date 10/04/2021 and it is giving me the due date of 10/18/2021 instead of 10/15/2021. I don't have dependencies enabled in my Project Settings and the formula I'm using is =WORKDAY([Start Date]@row, Duration@row). Please advise.
Thanks.
Answers
-
paste =WORKDAY([Start date]@row, 10) in the cell you want the date to appear, you can then copy the formula to the column so any new row automatically picks it up.
Hope this helps
Cheers.
-
Hi @Jason P,
Thanks for helping out. Unfortunately this formula won't work for the other tasks as the duration for each task is different and that's why I want a formula that's using the value in the "Duration (Days)" column, see below screenshot.
-
=WORKDAY([Start date]@row, [Duration (Days)@row)
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.9K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 79 Community Job Board
- 511 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!