Store past sprints in card module

10/13/21
Answered - Pending Review

Hi there!

Once I complete tasks and a 2-weeks sprint, how can I store them as completed or hide them, so I don’t need to see it in the Kanban/card board, but I can still search for it if needed?


Thanks!

Answers

  • Hi

    There are mutiplie solutions, such as:

    • Create on sheet per sprint, and one sheet for you backlog items so that when you start a spring you move some rows from you backlog to the new sprint.
    • Have all your stories into one sheet, and on status column add a value "closed". In you card view you can filter/hide items based on that value.
    • Create an automation so that rows are automaticly moved to an archive sheet once the statuts is set to "close".


Sign In or Register to comment.