We are using Smartsheet to manage a weekly work schedule. There is a workflow that sends "Request an update" to employees the ability to pickup an open shift. Do to volume of calculations and space limitations, the schedule is managed in a a master sheet:
- Master sheet is a two-week (14days) schedule
- Planning for new schedule starts 5days prior to the start date
There are instances when employees try to pick up a shift during the Planning, the work schedule is changed to the new coming two-week schedule
Is there a way to restrict the requests for update to 9days? Please note that we are not looking to create a unique bi-weekly schedule due to the overhead of all linked sheets for calculations.
Any feedback is appreciated.
Thank you in advance.
Gladys