Creating an Actual start, Actual finish and Actual Duration columns
Matt_GE
✭
Creating an Actual start, Actual finish, Actual Duration columns,
I have created those columns on my smartsheet for the purpose of tracking but I would like to make them default calculators for my project leaving my Start Date and End Date as baseline dates
But the columns I created would not allow dates to be altered with Smartsheet prompting me to remove predecessor links first in, I want to see my Actual duration column also calculating as I make changes to my actual start & actual finish dates
This seem to be proving really tough!!!! see snapshot
Anyone done this before ??? pls share the trick if you know, thanks
Matt_GE
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives