Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Creating an Actual start, Actual finish and Actual Duration columns
Matt_GE
✭
Creating an Actual start, Actual finish, Actual Duration columns,
I have created those columns on my smartsheet for the purpose of tracking but I would like to make them default calculators for my project leaving my Start Date and End Date as baseline dates
But the columns I created would not allow dates to be altered with Smartsheet prompting me to remove predecessor links first in, I want to see my Actual duration column also calculating as I make changes to my actual start & actual finish dates
This seem to be proving really tough!!!! see snapshot
Anyone done this before ??? pls share the trick if you know, thanks
Matt_GE
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives