Project Milestone Report
Deann Evans
✭✭
I am trying to create a report that shows multiple plan names in column 1 and then column 2-x shows milestones from the project plan with dates. I can't figure out how to do it.
Answers
-
I have done it before but can't recall how I did it.
-
You would create your report so that it is looking at all of the different sheets, pull in the various milestone and date columns and then ensure that the Sheet Name column is present.
-
@Paul Newcome but how did I pull in the various milestones? That is where I am stumped. because now it only shows me the standard column names (start, finish, assigned, etc).
-
@Deann Evans Did you try linking cells to the source sheet?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 349 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 455 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 282 Events
- 36 Webinars
- 7.3K Forum Archives