Dependency of tasks in gantt
Hallo together,
hope you can help me with this:
How would it be possible to create dependencies of tasks, meaning:
you cannot start with a task if another task is not done, f.e. you cannot start assigning the electrician before the room has not been constructed - right ;-)
Any solution ? ;-)
Best Answer
-
Hello,
I think I understand what you are asking. To have dependencies you will need to use the "Project" template. To do this click on the "Create" button and choose the third one down, "Project". The Predecessors column on this template will do what you are asking. In the properties for that cell you can change the dependency type.
Answers
-
Hello,
I think I understand what you are asking. To have dependencies you will need to use the "Project" template. To do this click on the "Create" button and choose the third one down, "Project". The Predecessors column on this template will do what you are asking. In the properties for that cell you can change the dependency type.
Help Article Resources
Categories
Check out the Formula Handbook template!