Project sheet
TaliRXM
✭✭✭
Hello,
I have created a 'simple' project sheet to track loaners.
A few questions:
- when updating "Assigned to" I see the same person's name appears on the calendar side (right). Does that mean that a reminder will be automatically sent to the person on the "Finish" date?
- the duration was calculated on the first row, but not on any other rows added. Why?
Thanks!
Answers
-
You need to update the Gantt project settings. The display label looks to be selected as Assigned to column. Modify Project Settings | Smartsheet Learning Center
-
Understood.
- So the display label whatever it is assigned to, is just a label, not a reminder to the person in the 'assigned to'? to be able to have a reminder, i need to set up one, correct?
- the other issue still not resolved: the duration was calculated on the first row, but not on any other rows added. Why?
Thanks!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives