Automate Risk Flag
I would like to automate the risk flag if the date is on or after the Target Date. I am new to smartsheet. having trouble with this. thank you
Answers
-
Hi @smartpmsg
I hope you're well and safe!
Try something like this.
=IF([Target Date]@row <> "", IF([Target Date]@row <= TODAY(), 1))
Did that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
âś…Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
@Andrée Starå Re: your formula, I was able to use it in the Risk Flag column. However, in addition to triggering the flag when the due date is in the past, I also need the added condition to only trigger if the Task Status is In Progress or Not Started. How do I add that?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.4K Get Help
- 364 Global Discussions
- 200 Industry Talk
- 429 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!