Dear all - I recently had to import a 500ish lines worth of .mpp plan. Upon import, the dates of the .mpp were not matching the dates of the Smartsheet plan.
I checked to see any custom holidays were imported and yes they were - I have a theory that the imported plan may have slack on some tasks which Smartsheet ignored and brought in auto scheduling? I am not sure.
Has anyone else encountered and be able to guide?
Thanks