How do I write a formula to flag an item when it is 40 days past the Start Date.

I have a Planned Start Date and added a 40 Post Start column where I would like either a Flag on or Yes would also work. Can't seem to get the syntax right!

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!