How do I write a formula to flag an item when it is 40 days past the Start Date.
I have a Planned Start Date and added a 40 Post Start column where I would like either a Flag on or Yes would also work. Can't seem to get the syntax right!
Best Answer
-
Hi @Jenann
I hope you're well and safe!
Try something like this.
=IF([Planned Start Date]@row >= TODAY(40), 1)
Did that work/help?
I hope that helps!
Be safe and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Answers
-
Hi @Jenann
I hope you're well and safe!
Try something like this.
=IF([Planned Start Date]@row >= TODAY(40), 1)
Did that work/help?
I hope that helps!
Be safe and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
That is great! Thanks so much for the fast response. This was so helpful 😀
-
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I thought that worked but it seems to be just flagging 40 days current day. What I need is flagging 40 days from the Planned Start day no matter what day it is. If start date is Mar 1, the flag would be yes on Apr 9 no matter what day it is that I look at it.