projects with simultaneous/concurrent tasks
Hi,
How do you track dependencies and predecessors for tasks that are happening simultaneously rather than in a linear fashion? This isn't every task but some can be accomplished at the same time. I'm struggling with how these should be displayed for a project.
Thanks!!
Best Answer
-
Hi @rebcesarz
What I would personally do is set up a "SS" relationship between these rows... a "start - to - start" relationship, so that both tasks have the same Start Date. Then you can use the one with the later finish date as the one to base the following tasks on for your linear path.
Here's more information on the types of relationships you can build, see the bottom of the article: Enable Dependencies and Use Predecessors
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @rebcesarz
What I would personally do is set up a "SS" relationship between these rows... a "start - to - start" relationship, so that both tasks have the same Start Date. Then you can use the one with the later finish date as the one to base the following tasks on for your linear path.
Here's more information on the types of relationships you can build, see the bottom of the article: Enable Dependencies and Use Predecessors
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives