Hello,
I am new to Smartsheet. My project is setup to have 5-day work. One of my project items will be ended on Saturday (say 3 Jun 2017). However, the system will automatically change the end date to 2 Jun 2017, Friday. How can I change the setting in Smartsheet to allow the end date on Saturday? Thanks a lot!
Update: I disabled dependencies in project settings, and the end date can be set on Saturday then.