How do I import a MSProjoject into SS reflecting the benchmark details
I have a client who is heavily invested into MS Projects, his template reflects his benchmarked dates as well as the actual start and end dates, when I import the project plan it does not reflect the benchmarked dates although I can view them in the original MS Project file. How do I get all this data in, please help, at my wits end, and really don't feel like going back to MS Projects.
Cheers Venn
Answers
-
Hi @Venn Cannon
It sounds like you may want to create a Baseline in your Smartsheet Sheet (here's a free webinar that goes over Baselines: Keep Your Projects on Track with Baselines).
What I would do is copy/paste in the Start and End dates for your baseline/benchmarks first, set the Baseline in Smartsheet, then copy/paste in the actual Start and End dates, which will update the Variance in the Baseline. See: Set Baselines on a Project Sheet
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.3K Get Help
- 462 Global Discussions
- 156 Industry Talk
- 506 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 517 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!