Is there a way to set custom number of days to a trigger?
I see an option for 90 and 180 days before. but need something that falls in between
Best Answer
-
Hello @ashley.c.LV
One approach would be to add a helper column in your sheet that is counting days. Instead of a date trigger, choose when rows changed. Select the helper column as your trigger. You could add the value in that trigger field as your custom value, or, alternatively, you could add it as a custom value in the Condition section.
As an example, here's one I have where I'm looking for late to be within 30-45 days of due date. In this particular automation, I look for this condition at a set time each month to issue reminders. Note I filtered the automation in the condition section. I was able to insert any value I desired as the days alerted.
Would this work for you?
Kelly
Answers
-
Hello @ashley.c.LV
One approach would be to add a helper column in your sheet that is counting days. Instead of a date trigger, choose when rows changed. Select the helper column as your trigger. You could add the value in that trigger field as your custom value, or, alternatively, you could add it as a custom value in the Condition section.
As an example, here's one I have where I'm looking for late to be within 30-45 days of due date. In this particular automation, I look for this condition at a set time each month to issue reminders. Note I filtered the automation in the condition section. I was able to insert any value I desired as the days alerted.
Would this work for you?
Kelly
-
Thanks. This is a round about way of doing it, but yes it seems to be a solution for me!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 449 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives