Creating a report of projects with tasks due in the next x days
I need to create a report that will report all projects that have tasks due in the next (for example) 10 days. It appears that it can be done but, the directions say to start on the "Analytics Page". I cannot find anything that tells me where to find the Analytics Page. Am I approaching this incorrectly? We work in the legal profession where deadlines are so critical. Please help me get started.
Thanks, Jerry
Best Answer
-
Hi Jerry
Quick question for you, do you have multiple project schedules that you want to report against?
What you want is possible with one or more project sheets.
Start with the Create button on the upper right and select Report
Then choose
Row Report
From there choose the sheet with the project OR the sheets with the projects
From here you maybe good but we can certainly provide more but you would choose the columns next, then filter the way you want EX: Finish (Due Date) in the next 10 days
You can do more with Grouping, Summarizing, and Sorting if needed as well.
I hope that helps, please let me know if you ah
Thank you,
Kevin
Happy to help if I can.
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer)
Answers
-
I also, need to list the upcoming due tasks for each of the identified projects.
Thanks, Jerry
-
Hi Jerry
Quick question for you, do you have multiple project schedules that you want to report against?
What you want is possible with one or more project sheets.
Start with the Create button on the upper right and select Report
Then choose
Row Report
From there choose the sheet with the project OR the sheets with the projects
From here you maybe good but we can certainly provide more but you would choose the columns next, then filter the way you want EX: Finish (Due Date) in the next 10 days
You can do more with Grouping, Summarizing, and Sorting if needed as well.
I hope that helps, please let me know if you ah
Thank you,
Kevin
Happy to help if I can.
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer)
-
Yes, I do have multiple projects. I have upward around 25 various projects.
Thanks,
Jerry
-
Kevin,
Thank you so much for your assistance. I never would have figured this out. Ithink this is really going to help. Actually we have 40 active various projects. I'm still working with it.
Thanks again, mate! You deserve a badge!
Jerry
-
I am trying to type a formula for this same view so that I can put the metric in my Dashboard, however the calculation is incorrect, its much larger count than actual. I want it to only include tasks due within the next 5 days. Please include the formula for this, here is mine that is NOT working…
=COUNTIF({Schedule Range | End Date}, <=TODAY(5))
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives