How do I account for leap years when substract 90 days from the target date?

Emi
ββ
Hello Smartsheet Experts,
How do I account for leap years when substract 90 days from the target date?
For example, if my target date is 4/30/2024.
Thank you
Answers
-
Hi @Emi,
to my knowledge, Smartsheet's internal calendar incorporates that info. So 4/30/2024 - 90 = 1/31/2024 and 4/30/2023 - 90 = 1/30/2023.
Hope this helps!
Stefan
Smartsheet Consulting, Solution Building, Training and Support.
Projects for Processes and for People.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.9K Get Help
- 474 Global Discussions
- 208 Use Cases
- 517 Announcements
- 5.6K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 84 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!