Cell update automation
I have a status column with list of 5 items, one of which is "completed" and a Percent Complete column text/number with formatting as a percentage. I have attached the automation, but it never updates the Status to complete when the Percent Complete is 100%
Answers
-
How does the percent complete change to 100%, if it depends on a cross sheet reference and/or a cell link then it will not work (as per Smartsheet's design).
-
The Percent Complete update by the task owner or myself. It is freeform text field we enter the value. There is no external or internal link to another cell.
-
How is the Status column being updated for the rest of the options?
-
Not sure what you are asking. Today the % Complete and Status are manually updated. I would like to create an automation to automatically update the Status field to "Complete with the % Complete is 100%. There are other status in the Status column, not started, in-progress, etc.
-
Try adjusting your trigger so that it runs when % Complete changes to 1.
-
That worked, thanks for the help
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.6K Get Help
- 405 Global Discussions
- 215 Industry Talk
- 456 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!