Allocation % Column

Does the allocation % column work? I'm finding that for one of my coworkers it is saying she is over-allocated even when her allocation is only 60%. 20% for three projects all given the same time. Could someone explain why this is or if there is a solution or explain how allocation works if I am not using it right.
Answers
-
Hi Benn
The allocation % column works properly, although there migh be something wrong with your setup. Could you describe more the issue ?
-
Essentially anytime she has a value that isn't 0 in her allocation % column it pops up as her being over-allocated. I don't know what's wrong with my sheet or how to fix it. Any help would be much appreciated.
-
allocation is a number between 0 and 1, mmaybe is come from that.
-
Hi @Benn10
Do you have other sheets with Legacy Resource Management enabled? If so, is it possible that this coworker is set up on a different sheet at 100% allocation for a specific task spanning your dates? This would mean any additional tasks would automatically make her over-allocated.
To check this, click the allocation alert icon for that row to open the Project Resource View which lists the sheets where resources in your project are assigned tasks. See: Legacy Resource Management and allocation
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.5K Get Help
- 466 Global Discussions
- 156 Industry Talk
- 510 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 520 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives