counting tasks in a project
Hi i have a sheet that i am counting the number of tasks that each resource has, it works fine if only one resource is on a task but if i have multiple resources it doesn't count that task, i am using the formula =COUNTIFS({Project Schedule- Assigned To}, $[Primary Column]@row, {Project Plan- Status}, [Column2]$9), any suggestions?
Answers
-
Hi @ShaunW
You can use the HAS function for multiple contacts in cell. You an try the below formula
=COUNTIFS({Project Schedule- Assigned To}, HAS(@cell, $[Primary Column]@row), {Project Plan- Status}, [Column2]$9)
Best Regards
Amit Wadhwani, Smartsheet CoE, Ignatiuz Software, Exton, PA
https://www.linkedin.com/in/amitinddr/
If my solution helped you, do not forget to mark it awesome
Best Regards
Amit Wadhwani, Smartsheet Community Champion
Smartsheet CoE, Ignatiuz, Inc., Exton, PA
Did this answer help you? Show some love by marking this answer as "Insightful 💡" or "Awesome ❤️" and "Vote Up ⬆️"https://www.linkedin.com/in/amitinddr/ -
many thanks that didn't quite work, if i add that statement into the string it just returns a zero
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!