It would be very helpful to re-baseline only highlighted parts of a gantt so you don't overwrite values which are not to be reset.
This update would be very beneficial for updating baseline target dates for specific tasks/milestones without it impacting the entire project!
Yes! This update is critical to Smartsheet staying current in the agile environment. The fact that you cannot add new rows and baseline ONLY those new rows is really bad PM practice. The proper fix for this is after the initial project plan baseline is done, please give us the option to
a) "Baseline Only Recently Added Rows (not already baselined)"
b) "Re-baseline all rows in sheet (existing baselines will be adjusted to current dates).
Thank you!!