Hello
I need to add the automated 'Schedule Health' to the summary section of the Schedules (for all active projects) - see photo #1 below - and include a 'Schedule Health' column next to the 'Initiative Status' column in our Summary Sheet - see photo #2 below.
The purpose of doing this is that the 'Schedule Health' is automated in Smartsheet, instead the 'Initiative Status' is manually updated by the project leads, so by having the two columns next to each other, it'll give us a way to compare what's happening/should happen.
For context - we manage about 60 projects, and 20 of them are closed - so I need to be able to identify which projects to upload the Status Health for and for any future ones.
Thank you for your help
Rossella
Schedule - Summary Section
Summary Sheet - Initiative Status column (next to which I need to add the Status Health Column)