Hi, I'm new to smartsheet formulas and need to calculate how many days until a item is due using the due date.
Answers
-
Hi @LeeC
I hope you're well and safe!
Try something like this.
NETDAYS (returns the number of days between the dates)
=NETDAYS(Start@row, Due@row)
NETWORKDAY (Returns the number of working days between two dates. Adds 1 day to the result if the start date is a non-working day)
=NETWORKDAY(Start@row, Due@row)
NETWORKDAYS (returns the number of working days between the dates)
=NETWORKDAYS(Start@row, Due@row)
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 213 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!