Hi,
I am wondering if anybody can help me with setting up a formula that flags Red, Yellow, Green, Grey based on Status and Due Date.
If the status is complete, grey.
If the status is not complete and the due date is more than 5 working dates days in the past , then yellow.
If the status is not complete and the due date is than 10 working days in the past more, then red.
If the status is blocked or on hold, flag it as red.
For reference, status column includes: in progress, not started, complete, on hold, blocked.
Otherwise, it displays Green.
Would very much appreciate a quick response!
Many thanks
Yaya