Change Predecessor Dependencies in Report
Dependencies in the predecessor column in reports are not viewable but I need some capability for users working from the report to update lag or lead days. If the row that is being viewed in the report is not the leading task in a line of dependent tasks, the user is only able to update duration (not the start date, finish date, or predecessor information). Is there a way to change dependent date cells in a report?
Answers
-
Hi @RKLRpp
You are correct that when using dependencies and looking at a dependent task in a Report, you'll only be able to edit the Duration of that row to update the dates of that task. (See: Working with start and end dates in reports)
I would suggest working from the source sheet with Filters to update this information!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!