How does Smartsheet determine % Complete for a subset of tasks?
Task 1 has 4 tasks: 0%, 100%, 20%, 0% complete. Smartsheet has Task 1 at 34% complete
Task 2 has 4 tasks: 0%, 100%, 0%, 0% complete. Smartsheet has Task 2 at 33% complete
Thank you.
Best Answer
-
If you are using the dependencies, it also takes the duration into account.
Answers
-
If you are using the dependencies, it also takes the duration into account.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.3K Get Help
- 364 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 444 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!