Dependency based on column

Sbott
Sbott โœญโœญโœญโœญ

Hi. I am hoping I am submitting this into the right area. I have a project that has columns instead of rows that are dependencies. I am needing the due dates to factor in only working days. Is there a setting or formula that can make this work. The columns are below. Thanks in advance

  • Start Creating Content - 11/7/22 (duration is 10 working days)
  • First Draft Due (dependent on the completion of Start) 11/18/22 (duration 2 days)
  • Review Returned (dependent on the completion of First Draft Due) 11/22/22 (duration 2 days)
  • Video Due (dependent on completion of Review Returned) 11/25/22 (duration 3 days)
  • Finish and Upload Content (dependent on completion of Video Due) 11/28/22 (duration 1 day)

Best Answer

  • Captain Cowtown
    Captain Cowtown โœญโœญ
    Answer โœ“

    Hi,

    I believe you can use the WORKDAY function to accomplish your goal. It works this way =WORKDAY(Original Date, # of workdays to add, range of holidays you would like excluded).

    Does this help?

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!