Dependency based on column
Hi. I am hoping I am submitting this into the right area. I have a project that has columns instead of rows that are dependencies. I am needing the due dates to factor in only working days. Is there a setting or formula that can make this work. The columns are below. Thanks in advance
- Start Creating Content - 11/7/22 (duration is 10 working days)
- First Draft Due (dependent on the completion of Start) 11/18/22 (duration 2 days)
- Review Returned (dependent on the completion of First Draft Due) 11/22/22 (duration 2 days)
- Video Due (dependent on completion of Review Returned) 11/25/22 (duration 3 days)
- Finish and Upload Content (dependent on completion of Video Due) 11/28/22 (duration 1 day)
Best Answer
-
Hi,
I believe you can use the WORKDAY function to accomplish your goal. It works this way =WORKDAY(Original Date, # of workdays to add, range of holidays you would like excluded).
Does this help?
Answers
-
Hi,
I believe you can use the WORKDAY function to accomplish your goal. It works this way =WORKDAY(Original Date, # of workdays to add, range of holidays you would like excluded).
Does this help?
-
Thank you @Captain Cowtown That is what I needed
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 142 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!