Dependency based on column

Sbott
โญโญโญโญ
Hi. I am hoping I am submitting this into the right area. I have a project that has columns instead of rows that are dependencies. I am needing the due dates to factor in only working days. Is there a setting or formula that can make this work. The columns are below. Thanks in advance
- Start Creating Content - 11/7/22 (duration is 10 working days)
- First Draft Due (dependent on the completion of Start) 11/18/22 (duration 2 days)
- Review Returned (dependent on the completion of First Draft Due) 11/22/22 (duration 2 days)
- Video Due (dependent on completion of Review Returned) 11/25/22 (duration 3 days)
- Finish and Upload Content (dependent on completion of Video Due) 11/28/22 (duration 1 day)
Best Answer
-
Hi,
I believe you can use the WORKDAY function to accomplish your goal. It works this way =WORKDAY(Original Date, # of workdays to add, range of holidays you would like excluded).
Does this help?
Answers
-
Hi,
I believe you can use the WORKDAY function to accomplish your goal. It works this way =WORKDAY(Original Date, # of workdays to add, range of holidays you would like excluded).
Does this help?
-
Thank you @Captain Cowtown That is what I needed
Help Article Resources
Categories
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!