Disable auto update of start dates for dependent tasks
Looks like there was a thread on this https://community.smartsheet.com/discussion/7262/forced-dates-when-dependency-is-enabled to disable auto-update of start dates when using the predecessor feature.. is this implemented?
Answers
-
Hi @mc12
If you're setting a Predecessor for a row, then the dates of that row are auto-updated based on that predecessor, configured by if you've set this as a FF, FS, SF, or SS type of relationship.
You can add Lag or Lead time to the row if you need buffer days between when a task ends and when the dependent task begins. (See: Work with Duration and Predecessors)
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!