Disable auto update of start dates for dependent tasks
mc12
✭
Looks like there was a thread on this https://community.smartsheet.com/discussion/7262/forced-dates-when-dependency-is-enabled to disable auto-update of start dates when using the predecessor feature.. is this implemented?
Tags:
Answers
-
Hi @mc12
If you're setting a Predecessor for a row, then the dates of that row are auto-updated based on that predecessor, configured by if you've set this as a FF, FS, SF, or SS type of relationship.
You can add Lag or Lead time to the row if you need buffer days between when a task ends and when the dependent task begins. (See: Work with Duration and Predecessors)
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!