How to restrict days of the week for task dates based on the person responsible for task?
Team member only works Mon/Tues, so only want dates for tasks assigned to them to fall on Monday or Tuesday, and therefore impact and adjust the schedule dates. Is there a way this can be done without going through whole project schedule manually & adjusting?
Answers
-
This is going to end up being a manual process as working days are set at the sheet level and not the user level.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives