How to restrict days of the week for task dates based on the person responsible for task?
Bridget_D
✭✭
Team member only works Mon/Tues, so only want dates for tasks assigned to them to fall on Monday or Tuesday, and therefore impact and adjust the schedule dates. Is there a way this can be done without going through whole project schedule manually & adjusting?
Answers
-
This is going to end up being a manual process as working days are set at the sheet level and not the user level.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.2K Get Help
- 451 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives