How to restrict days of the week for task dates based on the person responsible for task?
Team member only works Mon/Tues, so only want dates for tasks assigned to them to fall on Monday or Tuesday, and therefore impact and adjust the schedule dates. Is there a way this can be done without going through whole project schedule manually & adjusting?
Answers
-
This is going to end up being a manual process as working days are set at the sheet level and not the user level.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives