RAG Automation: Difference Between 2 Dates
Good Day Smartsheet Community:
I am Trying to Modify the Formula Below to Add Yellow if The Difference Between Plan Vs Actual is 4 Days Behind Plan, otherwise greater than 4 Days Behind Plan is Red
=IF([Milestone Date (Plan)]@row = [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Plan)]@row > [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Plan)]@row < [Milestone Date (Actual)]@row, "Red")))
Thanks
Best Answer
-
Hey
Sorry, I misunderstood.
Try this
=IF([Milestone Date (Plan)]@row = [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Plan)]@row > [Milestone Date (Actual)]@row, "Green", IF(AND([Milestone Date (Actual)]@row > [Milestone Date (Plan)]@row, [Milestone Date (Actual)]@row <= [Milestone Date (Plan)]@row + 4), "Yellow", IF([Milestone Date (Actual)]@row > [Milestone Date (Plan)]@row + 4, "Red"))))
Kelly
Answers
-
Hey @Kaleb
Try this
=IF([Milestone Date (Plan)]@row = [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Plan)]@row > [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Actual)]@row = [Milestone Date (Plan)]@row + 4, "Yellow", IF([Milestone Date (Actual)]@row > [Milestone Date (Plan)]@row + 4, "Red"))))
Does that work for you?
Kelly
-
Almost, but the Tolerance is Up to 4 Day Behind Plan is Yellow, and anything Greater than 4 Days behind Plan should turn Red. Plan = Actual is Green.
The See Screen Shot Below is 2 Days Behind Plan but The Milestone Health does not Turn Yellow:
-
Hey
Sorry, I misunderstood.
Try this
=IF([Milestone Date (Plan)]@row = [Milestone Date (Actual)]@row, "Green", IF([Milestone Date (Plan)]@row > [Milestone Date (Actual)]@row, "Green", IF(AND([Milestone Date (Actual)]@row > [Milestone Date (Plan)]@row, [Milestone Date (Actual)]@row <= [Milestone Date (Plan)]@row + 4), "Yellow", IF([Milestone Date (Actual)]@row > [Milestone Date (Plan)]@row + 4, "Red"))))
Kelly
-
Excellent! That worked Perfectly. Thanks
Help Article Resources
Categories
Check out the Formula Handbook template!