Subtotals on new column in Project Sheet

SunnyJ
✭✭
Hi, I have a project sheet on which I have added a column for expended hours. I would like that column to behave like the %completed column in that it auto subtotals through the project. Is there any way to do that?
Edit: Fount it
Answers
-
Hi @SunnyJ,
The %Complete column averages the percentages of children rows, and is weighted based off the Duration column.
What do you want the Expended Hours column's row totals to be based on?
-
Thanks Ray,.In fact you're right. The %column averages, whereas I just wanted to subtotal the children.