Subtotals on new column in Project Sheet
SunnyJ
✭
Hi, I have a project sheet on which I have added a column for expended hours. I would like that column to behave like the %completed column in that it auto subtotals through the project. Is there any way to do that?
Edit: Fount it
Answers
-
Hi @SunnyJ,
The %Complete column averages the percentages of children rows, and is weighted based off the Duration column.
What do you want the Expended Hours column's row totals to be based on?
-
Thanks Ray,.In fact you're right. The %column averages, whereas I just wanted to subtotal the children.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!