WBS formula question
I am using the WBS Template from Smartsheets and I would like to add a row at the top to capture the project name and percent complete. I would like to modify the WBS formula(s) to have this row be known as WBS element 0 and then have the parents for each stage of the project start at the WBS level 1, 2, 3, etc. (not 1.1, 1.2, 1.3 as pictured below). Any suggestions on how to modify?
Answers
-
Hi Maria,
Within the context of this template sheet, the following Column formula should achieve what you intend: =IF(Level@row = 1, 0, COUNT(ANCESTORS()) + Suffix@row - 1). See the example below for your reference:
Note, however, that if your add further levels of hierarchy to your tasks, this may stop working as desired in these sub-tasks.
I hope that this can be of help
Cheers!
Julio
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 494 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!