Days since Submission if not complete
Hello all. I love that I can come to you for help. Eternally grateful!
I tried to find this in other threads but could not get them to work for me.
I'd like to count the number of calendar days since the date in "Date Submitted" if the checkbox in "Review Complete" has not been checked. Thank you very much.
Best Answer
-
No trouble that's why we are all here to learn and help each other.
This should do the trick for you
=if([Review complete]@row=False,Today()-[Date submitted]@row,"")
Hope that helps
Thanks
Paul
Answers
-
No trouble that's why we are all here to learn and help each other.
This should do the trick for you
=if([Review complete]@row=False,Today()-[Date submitted]@row,"")
Hope that helps
Thanks
Paul
-
Paul, thank you very much for taking the time to answer. That works! I was trying to use 0 to indicate Review Complete was not checked. Thanks again!!!! Paula
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!