How to Auto-populate dates from Project Deadline
Hi there,
I am setting up timeline "project" templates for my team. We have a handful of projects each year and they all will follow this same process so the duration for tasks and logic "predecessors" are already built in. I want to be able to set a deadline in the Baseline Start/Finish column on the project complete row and then have the dates auto populate in that same BS/BF column all the way to the start of the project. This should be able to quickly show if a deadline is realistic and what is the latest possible date we can start certain tasks. How can I set up a dates that auto-populate based on a deadline date?
Thank you
Answers
-
You would structure your predecessors column to work backwards.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!