Sign in to join the conversation:
Does Smart Sheet support multiple calendars similar to Projects where you can setup custom work days? If it doesn't how can I assign separate working days for different groups?
Only one calendar per sheet.
You can try separating tasks into multiple sheets by working days and then combining the results back together using Reports.
I did something similar with periodic meetings and international holidays.
Craig
Thanks again Craig, your help is appreciated.
Craig,
Are you saying you can combine multiple calendar sheets into 1 calendar sheet to be displayed?
Brian
Hey, I am using the below formula→ =INDEX({Source_Sheet_Entire_Table}, MATCH([Unique ID]@row , {Source_Sheet_ID_Column}, 0), 1) Although the answer should be "Project details" mentioned in Column 1, it says #No Match. What am I doing wrong?
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…