I need to set certain weekend days as work days inside a project. Does anyone know how to do this?
I can set all days as working days and then add back in the weekends as nonworking days, but this seems laborious.
Thanks.
Hello,
Thanks for your post! If I understand correctly, you want to set specific weekend days as working days, similar to the "Non-working days" feature in project settings with the opposite function. This isn't currently a feature, but you can submit a product enhancement request with the quick link to the right. The workaround of entering all days as working days, then adding the non-working days back to the sheet would be one way to resolve this. Alternatively, for tasks that require labor on weekdays, create two sub-tasks for Saturday and Sunday.
Note that you can also use Elapsed Time in your Duration Column to ignore non-working days on specific tasks if needed (https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors)
I hope this helps clear some things up!
Kind regards,
Isaac
Smartsheet Support
I have inly one user in my trial account. When I am trying to upgrade to PRO plan it is defaulting for 2 users and not allowing me to upgrade the plan for only one user. Please help.
We are curious if anyone is experiencing issues with automations that are to generate emails. We've been seeing gaps with a number of these automation on various sheets, where the sheet will record a date of when the email was sent, but it is either never received by the recipients or it is received hours or a day later.…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…