Is there such a thing as a formula for WORKDAY for today? I.e. modifier is 0 instead of + or -
I'd like a field that can go off another field or (work on itself) that can adjust itself to the closest workday, for example.
=WORKDAY([Due in PROD]1, 0)
Try something along the lines of...
=WORKDAY(IF(ISDATE([Due in PROD]1), [Due in PROD]1, TODAY()))
Basically the IF portion will input whatever date is in the [Due in PROD] column. If there is no date, then it will input TODAY(). It will then run the WORKDAY function based off of that result.
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…