Sign in to join the conversation:
I have a due date and want to have the "Risk" green if the due date is more than 15 days out and the Status is not "Complete". How do I do this?
Within the Conditional Formatting dialog box (button in the middle of your toolbar, looks like a grid with some colour to the squares) you can click on the drop down arrow on the left hand side and select the AND condition to add a second condition.
I have added a screen shot to show you what I mean.
Hope this helps.
Debbie Sawyer Consultant & Training Manager
If you are talking about the RYGB symbol column... you will want to use a formula in the symbol column,
=IF([Due Date]@row - Today() > 15, "Green", IF([Due Date]@row < Today(), "Red", "Yellow")
The formula will count everything greater than 15 as Green, Due dates in the past as REd and everything inbetween as Yellow.
Hi
Is it possible to compare 2 date columns in IF statement and do colouring based on that?
I would like to have separate delivery date for each row.
Regards,
Areg
Hi Areg,
@Areg Vrtanesyan
Yes, it is. We’d use a so-called helper column to make it work. In my example I use a checkbox helper column. You can then use that in the conditional formatting.
Try something like this.
=IF(AND(ISDATE(DateA@row); ISDATE(DateB@row)); IF(NOT(DateA@row = DateB@row); 1; ""))
The same version but with the below changes for your and others convenience.
=IF(AND(ISDATE(DateA@row), ISDATE(DateB@row)), IF(NOT(DateA@row = DateB@row), 1, ""))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did that work?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
@Areg Vrtanesyan It is very possible. You would need to put the IF statement in it's own column, then set up the Conditional Formatting to run based on this third column.
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…