Is there a way to take the average of the RYG colors and roll it up to an overall summary for a section and then the overall section to the overall project summary? I've included a snapshot of what I'm talking about.
Hi Frank,
Yes, it is. You'd need to decide on the rules for when it should be R,, Y or G.
What are your criteria?
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
The end users decided an selects based on the task if it is red-at risk, green - on track, yellow in between on track and at risk. Some fields might be blank if it is not filled in but we would like to take the average of the colors and assign the overall status. I hope this makes sense.
Try something like this.
Add the formula to all parents in the status column.
=IF(AND(COUNTIF(CHILDREN(); "Green") > COUNTIF(CHILDREN(); "Yellow"); COUNTIF(CHILDREN(); "Green") > COUNTIF(CHILDREN(); "Red")); "Green"; IF(AND(COUNTIF(CHILDREN(); "Red") > COUNTIF(CHILDREN(); "Green"); COUNTIF(CHILDREN(); "Red") > COUNTIF(CHILDREN(); "Yellow")); "Red"; "Yellow"))
The same version but with the below changes for your and others convenience.
=IF(AND(COUNTIF(CHILDREN(), "Green") > COUNTIF(CHILDREN(), "Yellow"), COUNTIF(CHILDREN(), "Green") > COUNTIF(CHILDREN(), "Red")), "Green", IF(AND(COUNTIF(CHILDREN(), "Red") > COUNTIF(CHILDREN(), "Green"), COUNTIF(CHILDREN(), "Red") > COUNTIF(CHILDREN(), "Yellow")), "Red", "Yellow"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Would that work?
Andrée
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…