Is there a way to take the average of the RYG colors and roll it up to an overall summary for a section and then the overall section to the overall project summary? I've included a snapshot of what I'm talking about.
Hi Frank,
Yes, it is. You'd need to decide on the rules for when it should be R,, Y or G.
What are your criteria?
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
The end users decided an selects based on the task if it is red-at risk, green - on track, yellow in between on track and at risk. Some fields might be blank if it is not filled in but we would like to take the average of the colors and assign the overall status. I hope this makes sense.
Try something like this.
Add the formula to all parents in the status column.
=IF(AND(COUNTIF(CHILDREN(); "Green") > COUNTIF(CHILDREN(); "Yellow"); COUNTIF(CHILDREN(); "Green") > COUNTIF(CHILDREN(); "Red")); "Green"; IF(AND(COUNTIF(CHILDREN(); "Red") > COUNTIF(CHILDREN(); "Green"); COUNTIF(CHILDREN(); "Red") > COUNTIF(CHILDREN(); "Yellow")); "Red"; "Yellow"))
The same version but with the below changes for your and others convenience.
=IF(AND(COUNTIF(CHILDREN(), "Green") > COUNTIF(CHILDREN(), "Yellow"), COUNTIF(CHILDREN(), "Green") > COUNTIF(CHILDREN(), "Red")), "Green", IF(AND(COUNTIF(CHILDREN(), "Red") > COUNTIF(CHILDREN(), "Green"), COUNTIF(CHILDREN(), "Red") > COUNTIF(CHILDREN(), "Yellow")), "Red", "Yellow"))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Would that work?
Andrée
I have a form that will be filled out internally. There's a cell labeled "Department" which contains 8 dropdown list values. There's a another cell called "Executives" which are the leaders of these departments. In the form, I'm attempting to do a logic where when you choose a specific "Department", then the cell…
I shared access to a user to a specific folder under workspace A (folder is 2025-09-Service Factory). However, I can see that he's shown to have access to all the other child folders under 02-ACTIVE Initiatives. Why is that when I only shared out one folder? Is there a way to only share access to users to ONLY specific…
what i can do if all my existing smartsheet gant files can't be open after change my plan to Pro? what could be the reason ?