Hi.
Ive just signed up for the free trial as I have a live project and I need something like Smartsheet.
I can't seen to work out how to create a new Primary Column.
What do I do ?
Thanks..
Hi Michael,
Welcome!
If you've created a sheet, there already is a Primary Column. It's probably the first one. (bold text)
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
More information about the Primary Column: https://help.smartsheet.com/articles/504645-primary-column
Hi Thanks
I might have the terminology wrong !
Im looking to add a new task, with sub tasks.
Happy to help!
I think you mean Parents / Children.
Information about Parents/Children: https://help.smartsheet.com/articles/504734-hierarchy-indenting-outdenting-rows
Hi and thanks
I think its a parent row I am trying to create, with children- I have 24 in total.
I can't see how to create a parent ! The indent doesnt show because I on an empty row. How do I add a parent ?
M..
If you insert a row above the 24 children/subtasks, right click on the first subtask row and select insert above and write something in the cell. Then select all subtasks and click on the Indent button in the toolbar (left of the Font selector).
The first row will become the Parent, and the subtasks will be Children.
Did it work?
Hi John
I have 24 tasks
I just want to know how to create a parent/ task name.
I can then enter the action/ child.
ID 1 - QFH project 05/22/19 11/22/19
ID 2 Scaffold 05/25/19 12/04/19
ID 3 Masonry 05/27/19 07/31/19 Sub-task; Start and finish 05/27/19 06/28/19 07/27/19 07/30/19
I need to end up with a sheet with 24 different ID's
Thanks.
Do you need help with this now or do you want to wait until our meeting?
Have a fantastic weekend!
Andrée
Did you get it working?
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?