Hello! I'd like to show the % complete of each of these training modules on the associated parent rows. I've attached a screenshot. Happy to add/remove columns, etc...
Can someone please assist?
Hi Monica,
If you go into your Project Settings and select the column as a % Complete column, it will be automatically rolled up.
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Thanks for your reply! Unfortunately that doesn't seem to be an options as we aren't using dates?
Thanks for your reply! Unfortunately, this doesn't seem to be an option since we aren't using dates? I've attached a screenshot.
There is a manual way, as well. I'll get back to this post a little later.
Would this formula help?
=AVG(CHILDREN())
NOTE: be sure to change the column type to %
Happy to help!
I saw that it's answered already!
Let me know if I can help with anything else!
Andrée
Hmm, I feel like I'm missing something very obvious. I tried using the formula - =AVG(CHILDREN()) - but it results in something that I wasn't expecting. I would expect to see 75% here, but instead see 38%. Attaching screenshots. Any ideas? Thanks again!
Never mind! Figured it out! Instead of "=AVG(CHILDREN())" I needed "=Sum(CHILDREN())
:-) Thanks!
Excellent!
So you didn't want % Complete up to 100% but sum the % in total.
Glad you got it working!
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?